Supply Detailed Task Information

Explanation

This activity is used to supply detailed information for maintenance tasks before the tasks can be completed.

Prerequisites

To perform this activity, a task must exist. This task cannot be in the Finished status.

System Effects

As a result of this activity, detailed task information will be supplied and the task can be completed when reaching the Work Done status.

Window

Maintenance Order

Related Window Descriptions

Maintenance Order
Maintenance Order/Maint. Order Str.
Maintenance Order/Maint. Order Str./Supply Task Info
Maintenance Order/Maint. Order Str./Supply Task Info/Fault
Maintenance Order/Maint. Order Str./Supply Task Info/Modification
Maintenance Order/Maint. Order Str./Supply Task Info/Oper Param
Maintenance Order/Maint. Order Str./Supply Task Info/Material List 

Procedure

  1. Open the Maintenance Order window and query (F3) for the necessary maintenance order.
  2. Click the Maint. Order Str. tab. In the graphical object structure, select the required task row, and then click the Supply Task Info subtab.
  3. Click the Fault tab if you want to enter fault-specific information on the task.
  4. You can enter or change the value in the Fault Code and/or Cause Code fields. Use the List of values to select valid values.
  5. Save the information (F12).
  6. Click the Modification tab, to enter information on modification tasks. You can enter or change the next execution type and/or update information on the rename of a serial.
  7. In the Next Exec. Step field, select the new execution type. Valid values are: Initial Inspections, Continued Inspections and Terminating Action.
  8. Select the Terminate Inspections check box if you want to terminate the inspections of a modification.
  9. In the Exec. Remark field, enter any information on the modification execution.
  10. In the Rename Serials area you can enter or change rename-specific information on the serial.
  11. Save the information (F12).
  12. Click the Oper Param tab to enter operational parameter values on a task when finishing the task.
  13. Right click on the table of the window, and then click Suggest Operational Values. The Maintenance Date for Default Values dialog box opens.
  14. Enter a value in the Maintenance Date field.
  15. Click OK.
  16. Save the information (F12).
  17. Click the Material List tab to enter information on the material used on the maintenance task processed as a simplified work order. Note that this tab is only made available for tasks with distribution type Simplified Work Order.
  18. Create a new record (F5) in the table of the window.
  19. In the Part Number field, enter the part number of the consumed material. Use the List of Values to select a valid value.
  20. In the Quantity field, enter the quantity of material consumed.
  21. Save the information (F12).