Define Actual Markups

Explanation

This activity is used to enter actual markups which are markup values assigned to project cost/revenue elements. In this activity actual markups will be defined for a company and any new sales contracts created will automatically inherit these markups.

Prerequisites

Project cost/revenue elements should be predefined for the company in the Project Cost/Revenue Elements window.

System Effects

The predefined markups based on project cost elements will be used as a basis for defining which markups are available for a given sales contract.

Window

Sales Contract Basic Data

Related Window Descriptions

Sales Contract Basic Data/Markups/Actual Markups

Procedure

  1. Open the Sales Contract Basic Data window, click the Markups tab and then click the Actual Markups tab.
  2. Click in the Company ID field and query for the company that you want to define the markup on.
  3. Create a new record in the lower part of the window.
  4. In the Project Cost Elements field, use the List of Values to select a project cost element for which you want to define the markup.
  5. In the Markup field, enter a markup value to fit the project cost element.
  6. Click Save.