Simulate Routing Cost

Explanation

This activity is used to simulate costs for routing alternates independent of the routing alternate status.

Note: You cannot perform a cost per routing calculation for cost set 1. If part has a by-product, cost reductions related to the by-product will not be taken into consideration when part routings cost is simulated or viewed.

Prerequisites

This activity has the following prerequisites:

System Effects

As a result of this activity:

Window

Part Routing Cost

Related Window Descriptions

Part Routing Cost

Procedure

  1. Open the Part Routing Cost window and create a new record.
  2. In the Site field, click List and select the site for which you want to perform the cost calculation.
  3. In the Part No field, click List and select the part for which the calculation should be performed.
  4. In the Cost Set field, click List and select the cost set for which you want to perform the cost calculation.
  5. In the Routing Rev/Alt field click List and select the routing revision/alternate for which you want to perform the cost simulation.
  6. If you want to calculate the cost for a particular lot size, change the automatically fetched lot size in the Std Lot Size field.
  7. Save the record.
  8. Click Calculate in order to calculate the cost for the given combination of structure and routing.