This activity is used to create a configuration for a configurable part. When creating the configuration, you define the characteristics and options the customer wants when you sell or build it.

A configuration is a unique combination of characteristics and options that is used in conjunction with a configurable part. The configuration of a part can be initiated in IFS/Project Delivery, IFS/Manufacturing Standards, IFS/Customer Orders, IFS/CRM, IFS/Shop Order, and IFS/Dynamic Order Processing. It can also be initiated by an external application.

The status of the configuration is always set to Incomplete at the start of a configuration. The status will automatically be set to Complete when all mandatory and optional characteristics have a valid option value. When the status is Complete, connected project item lines can be processed further.

Characteristics set to hidden in basic data can be displayed during configuration if needed by using Show hidden rows.

If sales rules are connected to the configure part and revision, the sales rule engine is executed automatically when you open the window in create or edit mode. All sales rules are then executed upon any change of characteristic or option value in the configuration section. Use the Sales Rule Logger dialog box to analyze the sales rule evaluation. Use the Latest Changes dialog box to analyze the characteristics added, removed and modified with regard to the latest change in the configuration.

The following icons will be displayed in the Project Product/Item tab , Project Items and Project Item Navigator windows to indicate an incomplete configuration or changes in the configuration after the last build structure action had been performed, relevant to a project item. 

Icon Window
Project Product/Item tab and the Project Items window
Project Item Navigator

Prerequisites

System Effects

Window

Project Product
Project Item Navigator
Project Items

Related Window Descriptions

Create, Edit, View Configuration

Procedure

  1. If you are on the window in which the configurable project item is displayed (Project Product/Item, Project Item Navigator/General, Project Item Navigator/Consist of, Project Items) right-click, point to Configuration and then click Build Structure.
  2. The project item structure will be created and operation lines will be copied into the Project Item Navigator/Project Operations tab. The structure can also be built when you confirm the completion of the configuration.