Change Inventory Part Location in Project Delivery

Explanation

This option will allow a multi site company to move parts between its sites. The company will have the ability to send or receive any items required for a Delivery Project from another site that belongs to the project. This will help the company to meet demands from its delivery projects with ease and transfer parts to sites when the capacity on one site is high.

Prerequisites

System Effects

Window

Project Product
Project Item Navigator
Change Inventory Part Location

Related Window Descriptions

Project Product/Items
Project Item Navigator/Consist of
Change Inventory Part Location

Procedure

This option is available in the Project Product/Items tab and Project Item Navigator/Consist Of tab:

  1. In any of the above windows query for your project and select the parts that you wish to transfer.
  2. Right click and select the Change Inventory Part Location menu option.
  3. In the Move Inventory Partwindow enter a new line and specify the quantity you wish to transfer in the Qty to Move field along with the required site.
  4. Save the change.
  5. Observe that the Available quantity and the On hand quantity will change according to the change you made.