Evaluate and Add Modification Tasks to the Work Scope

Explanation

This activity is used to add one or more modifications to a work scope. Usually the mandatory modifications, due modifications and modifications included in the customer baseline (i.e., those which have not been complied with as yet) are transferred to the work scope. Apart from the required modifications and due modifications, you can choose the modifications you want added [or not] to the work scope. For instance, if a modification which is not due nor assigned to a serial exists, and this modification is applicable to a particular serial, you can choose to add [or not add] the modification to the work scope, as per your requirements.

When you want to manually add modifications to the work scope you need to select the All Not Complied option to populate the table in the window with modification records for which the Include in Work Scope? check box can be modified.
To view all modifications for the serial structure irrespective of whether the modifications have been complied with or not, select the All option. To only view the modifications that have been complied with select the All PCW option.
If you want to create a de-comply task(s) select the All option or the All PCW option. Note: A de-comply task must be created before the modification can be added to the work scope.
To view modifications that are currently included in the work scope and/or, if required to remove modifications from the work scope, select the All Running option.

Prerequisites

System Effects

Window

Task Summary 

Related Window Descriptions

Task Summary/Modification
Shop Visit/Visit Defaults/Modification Baseline
Define Work Scope/Work Scope Tasks
Define Work Scope/Define Work Scope/Affected Part Tasks

Procedure

Use the following procedure to add a task to the work scope:

  1. Open the Task Summary window. 
  2. Query (F3) for the work order for which you want to create the work scope.
  3. Click the Modification tab.
  4. Click the All Not Complied option to view the modifications that can be included in the work scope.
  5. In the table of the tab, select the Include in Work Scope? check box for the modifications you want to include in the work scope.
  6. Optionally, you can verify if the modification(s) and its affected parts have been included in a work scope.

Use this procedure to create a decomply task to be included to the works cope at a later date:

  1. Open the Task Summary window.
  2. Query (F3) for the work order for which you want to create the work scope.
  3. Click the Modification tab.
  4. Click either the All or All PCW option and identify the modifications that have been complied with that you want to decomply.
  5. Select the row, right-click and select the Create Decomply Task option. Confirm the decomply of modification task to complete the creation of the decomply task.
  6. Click the All Not Complied option to ensure that the decomply task is now visible to be included in the work scope.