Assign additional Tasks to the same Maintenance Order

Explanation

This activity is used to assign additional pending tasks to a maintenance order that has been released and for which work orders have already been generated. You can assign tasks only for the same top serial (or a serial in its structure) as the one currently on the maintenance order.

If additional tasks, including non routines and condition measurement tasks, without connected operations are assigned, the task will not be distributed automatically. Instead, it will be set to the Incomplete status. Before the task can be set to the Under Preparation status, a valid instruction (i.e., instruction for the part revision of the serial defined on the task) must be connected to it. Note that it is necessary to set the task to the Under Preparation status in order for it to be released and distributed to a work order.

Prerequisites

System Effects

Window

Maintenance Order

Related Window Descriptions

Maintenance Order
Maintenance Order/Assign Tasks
Maintenance Order/Assign Tasks/Pending Tasks

Procedure

  1. Open the Maintenance Order window and query (F3) for the necessary maintenance order.
  2. Click the Assign Tasks tab and then click the Pending Tasks sub tab.
  3. Select the Include Task? check box for the task you want assigned to the selected maintenance order.
  4. Save the information (F12).