Import Maintenance Workload
Explanation
This activity is used to import work orders from IFS/Maintenance. These work orders are considered resource breaks within CBS. Neither Maintenance break dates and times nor CBS break times can be modified.
Prerequisites
This activity has the following prerequisites:
- IFS/Maintenance must be installed.
- Either a CBS site or an Advanced Planning Board (APB) site must be defined
and enabled in the
Scheduling Basic Data window.
The work orders that will be imported as resource
breaks has to fulfill the following constraints:
- The work order site should be the same site where the
import is done for.
- The work order should be connected to a object
which represents a work center resource or a tool instance.
- The operational status on the work order should
be Obstructive.
- Planned finish date on the work order has to be
defined and should be before the end of the scheduling horizon
- Planned start date on the work order has to be
defined and should be after the start of the scheduling horizon.
- The work order status should be
Under Preparation, Prepared, Released or Started.
- The execution time needs to be defined on the work
order.
System Effects
As a result of this activity:
- The system deletes corresponding resource breaks for any closed or
canceled work orders when importing.
- The imported work orders are compared against the corresponding resource breaks. Any updated work orders will update the corresponding resource breaks
and the new work orders will create new resource breaks.
Window
Maintenance Import
Related Window Descriptions
Maintenance Import
Procedure A
- In the Site field, specify the site to which you want to import the maintenance work
orders. Use List to select from available sites.
- In the Work Center No field, specify for which work center you want to import
maintenance work orders. Use
List to select
from available work centers. If you specify no work center, work orders for all work centers
are imported. As an alternative to specifying the work
center number, you can specify the name of the tool that will be used for
importing Maintenance work orders in the Tool ID field. If you
specify no tool ID, work orders for all tool IDs are imported.
- In the Resource ID field, specify for which resource you want to import maintenance work orders.
Click List to select from available resources. If you specify no resource ID, work orders for all resource IDs are imported. As an alternative to specifying the resource, you have the option of specifying the name of the tool instance in the
Tool Instance field. If you specify no tool instance, work orders for all tool instances are imported.
specify no tool ID, work orders for all tool IDs are imported.
- In the Begin Date Offset and End Date Offset fields, specify the offset in number of days.
specify no tool ID, work orders for all tool IDs are imported.
- Click OK.
Procedure B
Click Schedule and follow the steps in the wizard.