Evaluate Project Exceptions

Explanation

This activity is used to study project exceptions that occur when the forecasted requirement for a part has been exceeded by the actual demand for it.

Prerequisites

N/A

System Effects

N/A

Window

Project Exceptions

Related Window Descriptions

Project Exceptions
Project Exceptions/Forecast Exceeded

Procedure

  1. Open the Project Exceptions window and query for the desired project.
  2. Click the Forecast Exceeded tab to view details of instances where part forecast has been exceeded by the actual demand.