Remove Entire Master Schedule - MS Level 1
Explanation
This activity is used to remove master schedules from a selected MS set for the entire site. This works as a complete bulk delete of master schedules for a certain level 1 MS set in a given site.
Prerequisites
This activity requires you to select only one master schedule set at a time.
System Effects
As a result of this activity, all master schedules connected to the selected MS set will be removed permanently from the MS level 1 part of the selected site.
Window
MS Level 1 Forecast Sets
Related Window Descriptions
MS Level 1 Forecast Sets
Remove Entire Master Schedule - MS Level 1
Procedure
- Open the MS Level 1 Forecast Sets
window.
- Populate the window.
- Select the MS set which you want to remove all the master schedules for a particular site.
- Right-click and then click Remove Entire Master Schedule.
- In the Site field enter the Site ID or use List to select a site.
- Click OK.
- All master schedules for the selected MS set in the site will be removed.
- A message will appear to confirm the number of records to be removed from the particular MS set.
- Click Yes to remove the dataset. Click No to go back to the MS Level 1 Forecast Sets window.