Connect PM Action

Explanation

Use this activity to link Separate PM Actions into structures. You can do that by selecting a superior PM Action, and then connecting underlying PM Actions. PM structures are useful when a job involves several maintenance organizations and you want a work order created for each maintenance organization.

Prerequisites

System Effects

As a result of this activity, a Separate PM Action is included in a structure. The following effects can also be observed depending on the information specified in the superior PM:

Window

Separate PM Action

Related Window Descriptions

Connections for Separate PM Action

Procedure

  1. Open the Separate PM Action window and query for an existing PM Action.
  2. Right-click and click Connections. The Connections for Separate PM Action window appears.
  3. Create a new record (F5).
  4. In the Connected PM No field, use the List of Values to select a PM Action.
  5. In the Revision field, use the List of Values to change the revision of the selected PM action if necessary. 
  6. Save the information (F12).