Use this tab to connect PNGs together. The multi project material requirement planning (MPMRP) process allows you to plan material transfers between connected PNGs, if necessary. Therefore the project activities under the two connected PNGs can transfer parts between each other.
Note: You can only connect the PNGs within the same site. When you connect two PNGs, all the other PNGs that are already connected to one PNG will be automatically connected to the other PNG and its connected PNGs.. When you disconnect a PNG, it will be disconnected from all the other PNGs to which it was connected.