Integrate into Visit Structure

Explanation

This activity is used to integrate work into a visit structure, for instance, faults that are not already reported to the maintenance organization can exist in a technical log and may need to be corrected during the maintenance visit. These faults can be reported in the system and included to an ongoing maintenance order.

Prerequisites

System Effects

Window

Maintenance Order

Related Window Descriptions

Maintenance Order
Maintenance Order/Assign Tasks
Maintenance Order/Assign Tasks/Pending Tasks

Procedure

  1. Open the Maintenance Order window and query (F3) for the necessary maintenance order.
  2. Click the Assign Tasks tab and then click the Pending Tasks sub tab.
  3. Select the Include Task? check box for the task you want assigned to the selected maintenance order.
  4. Save the information (F12).