Replan Maintenance Order

Explanation

This activity is used to replan the start and/or finish dates of the maintenance order. If an entire maintenance visit is decided to be performed at an earlier or a later date than initially planned, the maintenance order can be moved to a new required start date and, at the same time, the planned execution logic structure (ELS) connected to it will be moved without having to regenerate the ELS.

Prerequisites

To perform this activity, a maintenance order in the Under Preparation status must exist.

System Effects

Window

Maintenance Order

Related Window Descriptions

Maintenance Order
Maintenance Order/Exec. Logic
Maintenance Order/Exec. Logic/Gantt
Replan Maintenance Order

Procedure

  1. Open the Maintenance Order window and search for the necessary maintenance order with the Execution Logic Structure distribution type.
  2. Click the Exec. Logic tab and then click the Gantt sub tab.
  3. Right-click on the chart, and then click Replan Maintenance Order. The Replan Maintenance Order dialog box opens.
  4. In the Requested Start field, enter the date and time the maintenance visit is required to start.
  5. In the Requested Finish field, enter the date and time the maintenance visit is required to finish.
  6. If you want to reset the entire ELS back to how it was default generated, but based on the changed dates in the Requested Start and Requested Finish fields in this dialog box, select the Reset the Execution Logic Structure check box.
  7. Click OK.