Connect Purchase Order Line to Project Activity
Explanation
Use this activity to manually connect a purchase order
line to a project activity from the purchase order line itself. This activity
is performed to obtain the cost of the project activity of goods being requested for
the project through the purchase order.
Note that you can manually connect an existing
purchase order line to a project activity also from the project activity.
(Refer to the activity Connect Existing Object to Activity). Another alternative is to
handle a project demand by procuring material against the miscellaneous demand
on the project activity. In such situations, the connection between the project
activity and the purchase order line would be system generated.
Of the above alternatives, manually connecting a
purchase order line to a project activity from the line itself (described in
this activity), is the most efficient process of handling
purchase orders for a project activity. This is because it excludes the need to
access the project client when handling project supplies. If you have a demand
against inventory for a project activity, you can supply this by creating a
purchase order for that demand in a standard manner, and connecting it to
a project activity from the purchase order line itself.
Note that you will be allowed to receive customer owned
parts from a single customer to a project that is connected to another customer.
Prerequisites
- The purchase order line must be in the Released or Confirmed status.
- The purchase order line must not have been
connected to a project activity.
- The project to be connected must be in the Approved or
Started status.
- The project activity must be in the Released status to
be available.
- The demand code on the purchase order line must be
either Inventory Order or Non-Inventory Order.
- The site of the purchase order line must have been
defined as an allowed site for the connected project.
- The relevant posting type must have been specified
for the project code part.
- The project code part must not have been pre-posted with a financial
project.
- The purchase order line must not have been manually pegged
to a customer order line or a shop order requisition line.
- The purchase order line must not have any exchange
components.
- Project manual connections to purchase order lines
must have been made available on the Project Details/Project Manual Connections
tab.
System Effects
As a result of this activity:
- The purchase order line will be connected to the
project activity.
- The purchase order line will display details about
the project activity to which the line has been connected.
- The purchase order line will get a project pre-posting. (As the purchase
order line already exists, it may already have pre-postings. If pre-posting on
the code part already exists, they will be replaced by the project
pre-posting. If the project pre-posting has no value for a code part then the
existing pre-posting on the object will remain unchanged. Also the project and
activity sequence will be posted.)
- The Project Info/Connections tab and
the Project Details/Supply/Pur Order Lines tab will display
details of the purchase order line connected to the project activity.
Window
Purchase
Order
Related Window Descriptions
Purchase Order
Connect to Activity
Procedure
- Open the Purchase Order window, and query for the relevant purchase order.
- Select the required purchase order line, right-click, point to
Project Connections and then click Connect to Activity. The
Connect to
Activity dialog box opens.
- To select the activity to which you want
to connect the purchase order line, click on the Program ID field (or
the Project ID field if your project does not have a program ID).
- Click List, and use the List
of Values to select the program ID pertaining to the activity you want to select.
- You can continue to specify the criteria for the activity you want to select, by clicking on the
Project ID,
Sub Project ID, and Activity ID fields, and then selecting
values from the List of Values.
- Alternatively, you can enter the activity sequence in
the Activity Sequence field, or select it from the List of Values. (The activity sequence
can be obtained from the Project Info/Activity/Details tab.)
- Click OK to save the record.