Enter Payment Schedule
Explanation
A payment schedule will enable you to enter the down payments and retentions
connected to a purchase order that is sent to a supplier. The payment schedule
lines can be connected to the relevant invoice. The down payment can
be amortized when the supplier sends the invoice.
Prerequisites
A purchase order part or no part line must exist.
System Effects
- A payment schedule with down payments and retentions will be created.
- The payment schedule will be connected to the purchase order.
- Invoices will be connected to the payment schedule.
Window
Payment Schedule for Purchase Order
Related Window Descriptions
Payment Schedule for Purchase Order
Connect to Payment Schedule
Procedure
- Open the Purchase Order window and query for the required purchase
order.
- Enter a part or no part line as required.
- Right-click on the header part of the window and then click Payment
Schedules. The Payment Schedule for Purchase Order
window appears.
- Enter a new record and define the down payment amount.
- Release the purchase order and then you will be able to release the down
payment line by selecting the Released check box for the line.
- You can now either choose to make a direct payment or create an advance
invoice.
- To create an advance invoice, enter the relevant details on the Manual
Supplier Invoice window. Select the Advance Invoice
check box and enter the gross amount.
- Right-click, point to Purchasing, and then click
Connect to Payment Schedule to connect the invoice to the
payment schedule.
- The Connect to Payment Schedule dialog box appears.
Click New and enter the order number. You can use the List of Values
to select the appropriate number.
- The matched amount can be modified in the case where you do not want to
match the full amount of the down payment.
- Click OK to save the connection.
- You will be able to view the matched invoice line back in the lower
table of the Payment Schedule for Purchase Order window.
- Open the Mixed Payment window to enter the details to pay
the invoiced amount. Once the voucher is created, you will get an information
dialog box informing you of the payment.
- Once the goods are received and the final invoice for the delivery is
created, you will be able to match the invoice with the purchase order
receipt.
- On the Supplier Invoice window, right-click, point to Purchasing
and then click Match with PO Receipt.
- In the Post from Purchase Order dialog box that appears, you
will see the order number selected. Click OK to match with the
purchase order
receipt.
- If you have specified a retention for the payment schedule, you will
need to match the retention line with the final invoice. Right-click on the
invoice, point to Purchasing, and then click Connect to Payment
Schedule to connect the invoice to the retention. line.
- Since the down payment line will need to be amortized with the final
invoice, right-click on the invoice window and then click Advance Invoice.
- Select the relevant invoice to connect from the Advance Invoice
Reference dialog box. You can modify the amount to be amortized if
required.
- Save the invoice.
- In the Payment Schedule for Purchase Order
window you will see the planned, matched and amortized amounts as well
as the connected invoice lines.