Activities

After the project structure is created, you can register the activities related to the sub projects. This is done using Activities window, Project Navigator/Activity List tab or Project Navigator/Activity tab. Activities can be connected to other objects like Work Orders, Activity Tasks etc., that can report cost, hours, revenue and progress information to the activity. An activity has one of the following statuses: Planned, Released, Completed, Closed or Canceled. The activities can be broken down to smaller tasks. The tasks can then be connected to the activity. By using the Attachment panel you can connect documents to the activity.

You can use the Activity Class field to group/categorize activities. Activity classes are registered in Project Basic/Activity Class tab.

If IFS/Project Reporting is installed the activity will contain extra information about the activity hours and valid report codes.

Activity Statuses

Throughout its development, an activity can have the following statuses:

Planned

When an activity is created, it is automatically set to Planned status. From here, the activity can be released or canceled via the corresponding menu option.

Released

When the activity is in Planned status and the project is in Approved status, the activity can be changed to Released via the menu option Release. The activity is then released and can start. From there, the activity can be set to Planned, Completed, Closed or Canceled via the corresponding menu option. The activity cannot be canceled or re-planned if it has any connections registered. When the activity is released then it is possible to report hours on the activity. Some objects can only be connected if the activity is in Released status.

Completed

When the activity is in the Released status, it can be changed to Completed via the menu option Complete. When the activity is in Completed status it can be promoted to Closed or demoted to Released state by running the menu options Close or Reopen respectively. When the activity is completed it is not possible to add any new costs, revenues e.g. by reporting hours on the activity. Costs already confirmed can be completed, i.e. transactions related to hours reported can be transferred to Finance.

Closed

When the activity is in Released or Completed status, it can be changed to Closed via the menu option Close. When the activity is in Closed status it can be demoted to the Completed state by running the menu option ReOpen. When the activity is closed it is not possible to create any financial transactions on the activity.

Note: It is possible to close activities without reaching 100 % progress.

Canceled

When the activity is in Planned or Released status, it can be changed to Canceled via the menu option Cancel. The activity is then canceled. When in Released status, the activity can be canceled only if it has no registered connections. When the activity is in Canceled status, no further status changes can be done.

Connecting Objects to Activities

Different types of objects can be connected to an activity, for example Activity Tasks, Work Orders, Purchase Requisition Lines, Purchase Order Lines, Shop Orders, DOP Headers, Document Packages, Time Report Sheets. There are two types of connections; System connections and Manual connections. For further information on connections and a complete list of all objects that can be connected to an activity, refer About Activity Connections.

The connected objects report cost, hours, revenue and progress information to the activity. The type of information reported depends on the connected object. For details refer the About Cost, Hours and Revenue Reported to Activity and About Earned Value and Progress.

Project Navigator/Activity List

This tab presents all the activities for the selected sub project. It is intended to simplify access to data by presenting the data in a list from which you select the preferred activity.

Project Navigator/Activity

This tab contains a presentation of associated cost, revenue, hours related to the selected activity. You can also enter cost elements and their estimated values in this tab. Actual figures are updated by the objects connected to the activity.

Workflow

Creating: You can create activities in Project Navigator/Activity List tab, Project Navigator/Activity tab and in the Activities window.

Modifying: Activities can be modified in Project Navigator/Activity List tab, Project Navigator/Activity tab, Activity/General tab and in Activities window.

Removing: You can remove an activity by using the delete option in the application or by using the menu option Delete Activity. If you use the remove button, you must first remove all objects connected to it. For information on deleting connected objects, refer About Activity Connections