Project milestones specify one or several dates for planned revenues in the project. Examples of project milestones are: first payment when the specification is finished, next payment when the prototype is finished, and final payment when the product is delivered. We then have the following project milestones defining the milestone identification, milestone date, description, and planned revenue:
Milestone ID | Milestone Date | Description | Planned Revenue |
10 | 13.05.2014 | Specification finished | 10000 |
20 | 20.05.2014 | Prototype finished | 30000 |
30 | 28.05.99 | Final product delivered | 50000 |
Project/Milestones
Project Navigator
Project/Milestones
Define Project Milestones (Step
7 in the Create New Project Assistant)
From the Create New Project Assistant: