Reorganize Project Structure

Explanation

Perform this activity to reorganize the project structure by moving subprojects and activities. This can be done by updating the Parent Sub Project ID field in the Sub Projects window and updating the Sub Project ID field in the Activities window. Alternatively, the drag and drop method can be used in the graphical structure navigator in the Project Navigator window.

Prerequisites

System Effects

Window

Project Navigator
Activities
Sub Projects

Related Window Descriptions

Project Navigator
Activities
Sub Projects

Procedure

  1. Enter the ID for the new subproject, or select from List of Values (F8).
  2. Save the changes.
  1. Enter the new subproject ID in Parent Sub Project ID field or select from List of values (F8).
  2. Save the changes.
  1. Click the activity to be moved, drag it to the subproject, and drop the activity on the new parent.
  1. Click the subproject to be moved, drag it to the subproject or the project, and drop it on the new parent.