Add Project to Sub Contract
Explanation
One or more projects can be used to execute/perform a sub contract and so it
is possible to enter several projects on a contract. If a project is added to an
item directly, it is required to specify an activity for it. However, only one
activity can be defined as the default activity for a sub contract. This default
activity will be used to report cost from all the items that have not been
connected to an activity.
Prerequisites
- The sub contract header should exist.
- The sub contract and project should belong to the same company.
System Effects
- A project is added to the sub contract.
Window
Sub Contract
Related Window Descriptions
Sub Contract/Project
Procedure
- Open the
Sub Contract window and query (F3) for the
necessary sub contract.
- Click the
Project tab and create a new record (F5).
- In the Project ID field, enter the project. Use the List of
Values to select from all existing projects in IFS/Project that belong to
the same company as the sub contract (provided that you have access to these
projects). If required, enter an activity for the project and any relevant
notes.
- Alternatively, you can directly add a project in Project ID field
in the Sub Contract/Lines/Items/Items tab,
although here it will be compulsory add the activity as well. The project
and activity will be updated in the Projects
tab.
- Save the information (F12).