Change Sub Contract Currency
Explanation
This activity is used to change the currency on the sub contract. The
currency can be changed irrespective of the status of the sub contract.
Prerequisites
- A sub contract which is not the Frozen state should exist.
System Effects
- The sub contract currency is changed.
Window
Sub Contract
Sub Contracts
Related Window Descriptions
Sub Contract
Sub Contracts
Change Contract Currency
Procedure
- Open the
Sub Contract window or the
Sub Contracts window.
- Query (F3) for the necessary sub contract.
- Right-click anywhere in the header and then click Change Contract
Currency. The
Change Contract Currency dialog box opens.
- In the To Currency field, enter the currency to which it is to be
changed.
- If necessary, select the Replace Currency Codes and Convert
Item Values check boxes.
- In the Contract Rev field, enter the sub contract revision. Click
List to select a valid value.
- Click OK.