Change Sub Contract Line Item Status

Explanation

This activity is used to manually change the status of a contract line item to any of the following statuses:

When the line item is included in a call off, and that call off is released, the status of the line item is automatically set (from Planned) to Work In Progress. Likewise, when the valuation for the line item has been certified to a value equal to or more than the contract value of the item, the status automatically changes (from Work In Progress) to Completed.

Owing to the automatic status update feature, certain validations are carried out when you are manually changing the status. For example:

Note: When the line item is set to the Completed status, further updates will not be allowed on the item unless the corresponding valuation is modified.

Prerequisites

System Effects

Window

Sub Contract

Related Window Descriptions

Sub Contract/Items/Lines/Items

Procedure

  1. Open the Sub Contract window and query (F3) for the necessary sub contract.
  2. Click the Items tab and then click the Lines/Items sub-tab.
  3. Select the line item, right-click, point to Status, and then click the desired status.